Lakeview Civic Improvement Association

  • Home
  • Announcements & Notices

LCIA Updates, Announcements and Public Notices 

Here you will find links to updates, announcements and notices relevant to Lakeview and the LCIA's ongoing efforts to improve quality of life in Lakeview.  

We will do our best to update this page as frequently as possible.

April Construction Update for RR222 Lakeview North Group F & G

The below includes a summary of work recently completed and what to expect over the next two weeks as construction continues in your area. 

RR401 – NOFOG #1 – Lakeview North Group F & G (RR222) – District A

Previous Week Work Progress (4/6/26 – 4/10/26)

  • 6800 Vicksburg – Crews completed excavation and base installation south side Mouton St intersection and began forming the remaining ADA Ramps and sidewalks on both sides of the south side of Chapelle St. intersection.
  • 6500 General Diaz – Teams set up steel forms to pave the Gen. Diaz & Porteous intersection. Mandrel testing of sewer was completed on 4/6/26.
  • 6600 General Diaz – The west lane was formed, and the Pre-pour inspection passed on 4/7, allowing for a crew to pour the lane on 4/8.
  • 6700 General Diaz - Restoration work on the intersection of Chapelle St continued with road removal and base installation. Mandrel testing of sewer was completed 4/6.  
  • 6800 Gen Diaz - Dressing behind curb began.
  • 7100 General Diaz - Removal and base work at Conrad intersection: While excavating this intersection, the contractor discovered damaged drain infrastructure and buried water valves not mapped on plans. Work was added to address this finding. Despite this minor setback, crews still began installing the manhole and catch basin needed on the block on 4/7.
  • 6400 Memphis - Water testing began, and chlorination test taken 4/7 and passed 4/8/26. 
  • 6500 Memphis - Ongoing drain line installations progressed.
  • 6600 Memphis – Contractors continued waterline installation.

Next Two Weeks Expected Work Progress (4/13/26 – 4/17/26 and 4/20/26 – 4/24/26)

  • 6900 Colbert - Restoration work and cleanup activity begins.
  • 6800 Vicksburg – Intersection of Vicksburg & Chapelle will receive restoration work. 
  • 6500 General Diaz – Crews plan to complete paving work for all curbs, sidewalks, driveways, and ADA Ramps on the block.
  • 6600 General Diaz - Roadway work will begin.
  • 6700 General Diaz - Roadway work starts.
  • 6800 General Diaz – The north side of Mouton St. continues restoration as crews begin to Pave ADA Ramps.
  • 7100 General Diaz - Roadway work on the intersection of Conrad. 
  • 6400 Memphis - Waterline work continues to prepare for testing. 
  • 6500 Memphis - Drain work will proceed.

6600 Memphis - Waterline repairs and installation. A water closure to tie in the new 8" water main is scheduled for 4/22/26.

These updates are regularly posted to the Department of Public Works project page so they’re easy to reference as work progresses:

Lakeview North Group F & G


P.O. Box 24378 | New Orleans, LA 70184

Powered by Wild Apricot Membership Software